Newsletter Q4 2021

A lot has happened in the park since the last time, here is an update on what has happened during Q4.

 

Knohult

Activities since the last newsletter

  • All roads in the windfarm area are now drivable 
  • The electrical grid within the windfarm areagrid has been established and the restoring roadsides and cable trenches is remaining to be completed
  • Foundation casting is proceeding according to plan and expected to be completed during the first quarter of 2022.
  • Blasting within the windfarm area is assumed to be completed.

 

Ongoing and upcoming work 

  • The  rock anchoring of the foundations has started and is expected to be completed during the first quarter of 2022
  • During the next quarter preparations will begin for the delivery of the turbines, which is expected in april 2022

 

 

Älgön

Activities since the last newsletter

  • All roads in the windfarm area are now driveable Foundation casting is proceeding according to plan and expected to be completed during the first quarter of 2022.
  • All hardstand areas are under construction.
  • Blasting within the wind farm area are assumed completed.

Ongoing and upcoming work

  • The electrical grid within the windfarm area has started and is to be completed in the first quarter 2022.
  • The restoring of road sides and cable trenches has started.

 

If you have questions regarding the ongoing construction work in the park area or its vicinity, please contact Vindin Vedbo AB's representative on the site, Rainer Härkäniemi, mobile 070 325 50 89.