Newsletter Q1 2022

Newsletter Q1 2022

Winter has passed and Kanonaden has in the end of March transferred the site responsibility to Vestas. Following is an update on what has happened during the first quarter of 2022.

Read More
Newsletter Q4 2021

Newsletter Q4 2021

A lot has happened in the park since the last time, here is an update on what has happened during Q4.

Read More
Newsletter Q3 2021

Newsletter Q3 2021

Since the Q2 newsletter, a lot has happened in both park areas, including foundation work in Knohult and work on the park’s internal road network in Älgön.

Read More
Newsletter Q2 2021

Newsletter Q2 2021

Local Civil Contractor Kanonaden Entreprenad AB commenced construction of the access roads, hardstanding areas and foundations on the 1st March 2021, the wind park has progressed according to plan and works are on scheduled to commence the installation of the foundations in August 2021.

During the installation phase of the foundations, from August to December 2021, there will be an increasing number of transports to the park area. Each foundation will require an average of 40 concrete cars. The proposed transport route will be from Jönköping via the road sections 132 for Knohult and 975 for Älgön.

Read More