Newsletter Q3 2021

Q3 Newsletter

 

The work with the parks' infrastructure is progressing as planned, below is an update on what has happened during the period.

 

Knohult

Activities since the last newsletter

  • Majority of trenches for the internal grid are prepared and ready for cable laying.
  • All planned blasting works are completed.
  • Foundations are casted weekly.

     

Ongoing and upcoming work

  • Work on the internal cable grid is progressing and expected to be completed the fourth quarter of 2021.
  • The need for further blasting may occur in conjunction to remaining excavation work for cable trenches.
  • Casting of foundations progresses according to schedule with the planning of all foundations to be completed the fourth quarter of 2021. Most transports take place on Tuesdays.

 

Älgön

Activities since the last newsletter

  • The park's internal access roads network has progressed and is approximately 80% established
  • The towers' s staging areas (Hardstand area) next to the wind turbines are approximately 45% established.
  • The works on foundations has commenced.

     

Ongoing and upcoming work

  • The wind farms internal access road network continues and is expected to be completed during the fourth quarter of 2021.
  • The work on foundations continues with the schedule to be completed during the first quarter of 2022.
  • The need for further blasting is expected in conjunction to the excavation work for roads, foundations, and cable trenches.

 

If you have questions regarding the ongoing construction work in the park area or its vicinity, please contact Vindin Vedbo AB's representative on the site, Rainer Härkäniemi, mobile 070 325 50 89. 